CBA Council Project Cost Benchmark

This page tests whether an Auckland Council, Auckland Transport, Eke Panuku or Watercare project cost is reasonable by comparing its cost per kilometre (or per lane-km or m2) with published New Zealand benchmarks. Of the 23 Auckland projects we rated, 7 are far above benchmark, 1 is well above, 6 are above and 9 are within. Use the calculator to test any other project.

Calculator

$195m per km in 2025 dollars, 1.49× the benchmark: Above benchmark

Opens on the Eastern Busway, Pakūranga to Botany: official $867m budget (October 2021) over 5 km.

Advanced
Benchmark band
$68.0m to $131m, median $68.0m
Band basis
Full range of the three completed NZ busways in Te Waihanga Table 40 ($68m, $68m, $131m per km, 2025 NZD). Indicative only: three projects.
Source
Te Waihanga 2026, Table 40 (see busway band check)
Escalation applied
3% a year, factor 1.126
Index to use
CGPI civil construction
Te Waihanga stated figure (comparison only): $140m, p.47
1.39× $140m

The form opens on the Eastern Busway, Pakūranga to Botany, using its official $867m budget (October 2021) over the 5 km of busway AT gives for that section. It is brought to 2025 dollars at the 3% long-run rate as a rough guide only. A fixed annual rate is a shortcut; for a formal submission, take the actual quarterly CGPI values from Stats NZ Infoshare and use the index toggle. Te Waihanga figures are already in 2025 dollars: enter them with year 2025, and do not apply the 5.2% rate to reach June 2026 dollars unless you lift the band by the same amount.

  • Within: up to 1.0×
  • Above: over 1.0× to 1.5×
  • Well above: over 1.5× to 2.0×
  • Far above: over 2.0×

Auckland project ratings

CBA analysis, as at 17 November 2026

ProjectCost per km (or lane-km)Multiple of benchmarkRating
SH1 Papakura to Drury South Stage 1NZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. Widening; Te Waihanga dates the cost 2021.
Unit cost worked out
$90.0m per lane-km: $810m (2025 dollars) ÷ 9 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
6.29×
Caveat
Te Waihanga's 2025-dollar figure. A widening: Te Waihanga's band is built from new roads only, so this comparison is indicative.
$90.0m per lane-km6.29×Far above benchmark
Ō Mahurangi Penlink
Details
Stage
NZTA. Under construction. On 25 March 2026 NZTA said opening is now late 2029, around 12 months later than previously anticipated. '2021' in Te Waihanga is a cost-estimate date, not completion.
Unit cost worked out
$65.4m per lane-km: Te Waihanga's $915m (2025 dollars) ÷ 14 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
4.57×
Caveat
NZTA's estimate is $830m as at June 2022 (Ministry of Transport RIS, finalised 14 October 2022, p. 4). Te Waihanga's $915m is the same estimate restated in 2025 dollars (Table 29, p. 72). On 25 March 2026 NZTA said the $830m 'is expected to increase due to programme delays' and that it is assessing the cost impact. A 7 km road that includes the Wēiti River Bridge, so the motorway band is a weak comparison; against NZTA's $17m target it is still 3.85×.
$65.4m per lane-km4.57×Far above benchmark
Mill Road Stage 1
Details
Stage
NZTA. Investment case April 2025. NZTA's substantive Fast-track application was deemed complete on 23 October 2026. Not yet in construction.
Unit cost worked out
$62.5m per lane-km: lower end $1,750m ÷ 28 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
4.37×
Caveat
The $1.75bn to $2.05bn envelope is 'to design, consent, acquire land and construct', so land, design and consenting are inside the figure. High end gives $73.2m per lane-km (5.12×).
$62.5m per lane-km4.37×Far above benchmark
City Rail Link
Details
Stage
City Rail Link Ltd. Complete; passenger services from 13 September 2026.
Unit cost worked out
$1,592m per route-km: $5,493m revised total requested by City Rail Link Ltd (March 2023) ÷ 3.45 km twin tunnels
Benchmark used
OECD tunnelled heavy rail P75: $493m
Multiple of benchmark
3.23×
Caveat
Not restated in 2025 dollars. $5.493bn is the revised total City Rail Link Ltd requested on 15 March 2023, funded by the sponsors in 2023; no final cost has been published. The total includes two new underground stations, the redeveloped Maungawhau and conversion of Waitematā to a through station, so a per-km comparison is harsh on scope.
$1,592m per route-km3.23×Far above benchmark
Te Ara Hauāuru, Northwest Busway (Stage 2)
Details
Stage
NZTA. Investment case April 2025; construction not started (as at April 2025).
Unit cost worked out
$410m per km: Stage 2 envelope lower end $4,100m on Te Waihanga's two-way-equivalent route length (Table 40, p. 85)
Benchmark used
Busway: $131m
Multiple of benchmark
3.13×
Te Waihanga stated figure (comparison only)
2.93× of $140m
Caveat
Te Waihanga does not say which section its length covers. The official project area is 18 km along SH16 (Brigham Creek to the city centre). $4.1bn to $4.6bn is Stage 2 only, includes the Newton city-centre connection, and factors in 30% for escalation and administration. If that 30% is treated as a mark-up and removed, it is about $315m per km: 2.41× the $131m band top (2.25× the Te Waihanga stated figure of $140m, comparison only), still far above. Figures as at April 2025.
$410m per km3.13×Far above benchmark
Lincoln Road corridor improvements, HendersonAuckland Transport local road
Details
Stage
Auckland Transport. Estimate approved for funding by NZTA Board, 9 June 2017; completion and final cost not verified.
Unit cost worked out
$31.1m per added lane-km: $80.9m estimate (including $32.4m property) ÷ 2.6 added lane-km (1.3 km, one transit lane added each way)
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
2.18×
Caveat
A 2017 estimate in 2017 dollars, not an outturn. Includes $32.4m of property; without property it is $18.7m per added lane-km (1.30×). An urban arterial widening with cycleways, a raised median and intersection upgrades, compared with a new motorway band, so indicative only. Length: 1.3 km (AT Notice of Requirement AEE).
$31.1m per added lane-km2.18×Far above benchmark
Ara Tūhono, Warkworth to Te Hana
Details
Stage
NZTA. PPP financial close 30 July 2026; early works from August 2026; main construction starts November 2027; opening expected 2033.
Unit cost worked out
$28.7m per lane-km: lower 2023 estimate of $2,981m (2025 dollars) ÷ 104 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
2.004×right on the 2× line
Caveat
Right on the 2× line: 2.004 times the band top, so far above by a 0.2% margin. A 2023 estimate, not the contract price. A present-value figure for the PPP is published, but it covers design, build, finance, maintenance and operation over 25 years, so it cannot be used as a cost per km. Includes an 850 m twin-bore tunnel. Against NZTA's $17m Upper North Island target (Te Waihanga, p. 34) it is 1.69×, well above rather than far above.
$28.7m per lane-km2.004×right on the 2× lineFar above benchmark
SH1 Manukau to Papakura wideningNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. Widening; Te Waihanga dates the cost 2021.
Unit cost worked out
$23.9m per lane-km: $440m (2025 dollars) ÷ 18.4 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.67×
Caveat
Te Waihanga's 2025-dollar figure. A widening: Te Waihanga's band is built from new roads only, so this comparison is indicative.
$23.9m per lane-km1.67×Well above benchmark
SH20 Mt Roskill ExtensionNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2009.
Unit cost worked out
$20.5m per lane-km: $328m (2025 dollars) ÷ 16 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.43×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$20.5m per lane-km1.43×Above benchmark
SH1 Northern GatewayNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2009.
Unit cost worked out
$19.0m per lane-km: $570m (2025 dollars) ÷ 30 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.33×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$19.0m per lane-km1.33×Above benchmark
Eastern Busway, Pakūranga to Botany
Details
Stage
Auckland Transport. Under construction, 2023 to 2027.
Unit cost worked out
$173.4m per km: official $867m budget (2021 dollars) ÷ 5 km, before escalation
Benchmark used
Busway: $131m
Multiple of benchmark
1.32×
Te Waihanga stated figure (comparison only)
1.24× of $140m
Caveat
Official $867m budget (October 2021) in 2021 dollars, before escalation; escalating to 2025 dollars would raise it. Te Waihanga's own $171m per km gives 1.31×. Includes the Reeves Road flyover. See the Eastern Busway check below.
$173.4m per km1.32×Above benchmark
Murphys Road upgrade, Flat BushAuckland Transport local road
Details
Stage
Auckland Transport. Reopened as a four-lane road, September 2020.
Unit cost worked out
$17.4m per added lane-km: $29.5m ÷ 1.7 added lane-km (850 m, one lane added each way)
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.21×
Caveat
Nominal 2017 to 2020 dollars, not escalated. Includes a new stream crossing (triple-box culvert), a shared path, signals and undergrounding of overhead services. Widening of an urban arterial, compared with a new motorway band, so indicative only. Length and added lanes from AT's tender notice (GETS, 369-17-770-AC).
$17.4m per added lane-km1.21×Above benchmark
SH16 Lincoln to Westgate wideningNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. Widening; Te Waihanga dates the cost 2019.
Unit cost worked out
$15.8m per lane-km: $142m (2025 dollars) ÷ 9 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.10×
Caveat
Te Waihanga's 2025-dollar figure. A widening: Te Waihanga's band is built from new roads only, so this comparison is indicative.
$15.8m per lane-km1.10×Above benchmark
SH1 Puhoi to Warkworth
Details
Stage
NZTA. Complete; Te Waihanga dates the cost 2020.
Unit cost worked out
$15.3m per lane-km: $1,132m ÷ 74 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
1.07×
Caveat
Just over the band top. Publicly reported outturn figures have varied.
$15.3m per lane-km1.07×Above benchmark
Eastern Busway, Panmure to Pakūranga
Details
Stage
Auckland Transport. Complete, 2018 to 2021.
Unit cost worked out
$131m per km: $340m ÷ 2.6 km
Benchmark used
Busway: $131m
Multiple of benchmark
1.00×
Te Waihanga stated figure (comparison only)
0.94× of $140m
Caveat
Matches Te Waihanga Table 40; it sets the top of the $131m busway band.
$131m per km1.00×Within benchmark
Airport to Botany Busway
Details
Stage
AT and NZTA. Business case and route protection.
Unit cost worked out
$124m per km: $2,227m ÷ 18.0 km (123.7 unrounded)
Benchmark used
Busway: $131m
Multiple of benchmark
0.94×
Te Waihanga stated figure (comparison only)
0.88× of $140m
Caveat
Te Waihanga's $2,227m is not printed in the 2021 business case, which gives its own P50 and P95 ranges including property.
$124m per km0.94×Within benchmark
SH20 Manukau ExtensionNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2011.
Unit cost worked out
$11.8m per lane-km: $319m (2025 dollars) ÷ 27 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
0.83×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$11.8m per lane-km0.83×Within benchmark
Te Honohono ki Tai, Matakana Link RoadAuckland Transport with NZTA, local road
Details
Stage
Auckland Transport with NZTA. Completed June 2023.
Unit cost worked out
$11.5m per lane-km: $62.2m (design, land and construction) ÷ 5.4 lane-km (1.35 km, four lanes)
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
0.81×
Caveat
Nominal dollars (2020 to 2023), not escalated to 2025. Includes land, a bridge, off-road walking and cycling and wetlands. A new urban arterial rather than a motorway. Four lanes along the full length per the Government release of 30 June 2020.
$11.5m per lane-km0.81×Within benchmark
SH16 Upper Harbour to HobsonvilleNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2012.
Unit cost worked out
$9.6m per lane-km: $322m (2025 dollars) ÷ 33.6 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
0.67×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$9.6m per lane-km0.67×Within benchmark
SH16 Upper Harbour to GreenhitheNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2007.
Unit cost worked out
$7.6m per lane-km: $198m (2025 dollars) ÷ 26 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
0.53×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$7.6m per lane-km0.53×Within benchmark
Northern Busway
Details
Stage
Complete, 2008.
Unit cost worked out
$68m per km: $504m ÷ 7.45 km
Benchmark used
Busway: $131m
Multiple of benchmark
0.52×
Te Waihanga stated figure (comparison only)
0.49× of $140m
Caveat
Bottom of the band. Original outturn not re-verified.
$68m per km0.52×Within benchmark
Northern Busway extension
Details
Stage
Complete, 2022.
Unit cost worked out
$68m per km: $341m ÷ 5.0 km
Benchmark used
Busway: $131m
Multiple of benchmark
0.52×
Te Waihanga stated figure (comparison only)
0.49× of $140m
Caveat
Bottom of the band. Original outturn not re-verified.
$68m per km0.52×Within benchmark
SH1 Albany to SilverdaleNZTA state highway, Te Waihanga Table 29, p. 72
Details
Stage
NZTA state highway. New road; Te Waihanga dates the cost 2000.
Unit cost worked out
$5.1m per lane-km: $287m (2025 dollars) ÷ 56 lane-km
Benchmark used
NZ motorway P75: $14.3m
Multiple of benchmark
0.36×
Caveat
Te Waihanga's 2025-dollar figure. This new road is one of the 25 projects that make up the band itself.
$5.1m per lane-km0.36×Within benchmark

Several inputs are estimates or envelopes, not outturn costs. See Sources and checks for exclusions.

Nine of the added projects are NZTA state highway projects in Auckland, taken from Te Waihanga Table 29, p. 72. The three Auckland Transport local road projects are compared with the motorway band per added lane-km (or per lane-km for a new road) because it is the only road band on this page.

Multiple of the benchmark, by project

SH1 Papakura to Drury South Stage 1
Ō Mahurangi Penlink
Mill Road Stage 1
City Rail Link
Te Ara Hauāuru, Northwest Busway (Stage 2)
Lincoln Road corridor improvements, Henderson
Ara Tūhono, Warkworth to Te Hana
SH1 Manukau to Papakura widening
SH20 Mt Roskill Extension
SH1 Northern Gateway
Eastern Busway, Pakūranga to Botany
Murphys Road upgrade, Flat Bush
SH16 Lincoln to Westgate widening
SH1 Puhoi to Warkworth
Eastern Busway, Panmure to Pakūranga
Airport to Botany Busway
SH20 Manukau Extension
Te Honohono ki Tai, Matakana Link Road
SH16 Upper Harbour to Hobsonville
SH16 Upper Harbour to Greenhithe
Northern Busway
Northern Busway extension
SH1 Albany to Silverdale
Benchmark top
6.29×
4.57×
4.37×
3.23×
3.13×
2.18×
2.004×
1.67×
1.43×
1.33×
1.32×
1.21×
1.10×
1.07×
1.00×
0.94×
0.83×
0.81×
0.67×
0.53×
0.52×
0.52×
0.36×

Frequently asked questions

What is the CBA Council Project Cost Benchmark?

A repeatable test for whether an Auckland Council, Auckland Transport, Eke Panuku or Watercare project cost is reasonable: normalise it to a unit cost, bring it to the benchmark year with a named index, compare it with a sourced band, and rate it.

How is a project rated?

Divide the normalised unit cost by the top of the benchmark band. Up to 1.0× is within benchmark, over 1.0× and up to 1.5× is above, over 1.5× and up to 2.0× is well above, and over 2.0× is far above. A cost under the bottom of the band is flagged to check scope and exclusions.

How are older costs brought to the benchmark year?

Use Stats NZ CGPI civil construction for roads, water and transport, and CGPI non-residential buildings for facilities. Multiply by the index at the benchmark date divided by the index at the cost date. A fixed annual rate is a shortcut only.

How does the Northwest Busway compare?

On Te Waihanga's figures, Te Ara Hauāuru, Northwest Busway (Stage 2) works out at $410m per km: 3.13× the $131m top of the completed-busway band (2.93× the Te Waihanga stated figure of $140m, comparison only). The official project area is 18 km, and the $4.1bn to $4.6bn envelope factors in 30% for escalation and administration. If that 30% is treated as a mark-up and removed, it is about $315m per km, still far above.

What are the main limits of this benchmark?

Bands rest on small samples (for example 25 NZ motorways, 4 NZ hospitals, 3 completed NZ busways), RLB building rates are Q4 2024, and no sourced public benchmark was found for libraries, pools, community centres, or water and wastewater pipes and plants. Ratings are a snapshot as at 17 November 2026, and several inputs are estimates or envelopes, not outturn costs.

How we worked this out

The method

  1. 1

    Define the scope and the unit

    Roads per lane-km, busways and rail per route-km, buildings per m2 of gross floor area. Record what is in and out of the number: land, GST, fees, contingency, escalation, financing.

  2. 2

    Make it like-for-like with the benchmark

    RLB building rates exclude GST, land, legal and professional fees, loose furniture, and site works and drainage, so strip those out. Te Waihanga road and busway figures are whole-of-project costs, so compare total project cost.

  3. 3

    Bring it to the benchmark year

    Use Stats NZ CGPI civil construction for roads, water and transport, and CGPI non-residential buildings for facilities. Benchmark year = index at benchmark date ÷ index at cost date.

  4. 4

    Note the estimate's confidence level

    A P95 or "upper" business-case figure carries more risk allowance than a P50. Record which it is before rating.

  5. 5

    Compare with the band and rate it

    Divide the normalised unit cost by the top of the band and apply the thresholds below.

  6. 6

    Ask for the cost build-up when out of band

    Use the document checklist and the LGOIMA wording on this page.

Rating thresholds

RatingTest (normalised unit cost vs the top of the band)Why this line
Below bandUnder the bottom of the bandLow numbers can mean missing scope; Oxford Global Projects found optimism bias drives overruns.
Within benchmarkUp to 1.0×Inside the published P25 to P75 or low to high range.
Above benchmarkOver 1.0× and up to 1.5×Published P80 risk uplifts run 15% to 68% by project type, and Te Waihanga puts cross-country conversion error at up to ±20%. A gap this size can be risk allowance or data noise, so ask questions.
Well above benchmarkOver 1.5× and up to 2.0×Larger than typical risk allowances. Ask for the cost build-up and scope drivers.
Far above benchmarkOver 2.0×Te Waihanga notes that even decades of escalation at about 3% a year explain unit costs about twice present-day levels, not more.

Nine of the added rows are NZTA state highway projects in Auckland from Te Waihanga Table 29, p. 72, and are compared with the NZ motorway P75 band of $14.3m per lane-km. Three Auckland Transport local road projects (Lincoln Road corridor improvements, Murphys Road upgrade, and Te Honohono ki Tai) are also compared with that band: the two widenings use cost per added lane-km, and the new road uses cost per lane-km, because it is the only road band on this page. This is indicative only for urban arterials. SH1 Albany to Silverdale is one of the 25 projects that make up the motorway band itself. The other added new-road rows from Table 29 carry the same caveat.

NZ benchmark bands

Roads

BenchmarkUnitLowMedianHighBase yearSource
Motorway / expressway, NZ completed (pre-2022)NZ$m per lane-km$7.6m$8.6m$14.3m2025Te Waihanga 2026, Table 28
Motorway, NZTA indicative target, Upper North IslandNZ$m per lane-km$14.0m$17.0m2025Te Waihanga 2026, p.34
Motorway / expressway, OECD countriesNZ$m per lane-km$3.0m$5.5m$8.8m2025Te Waihanga 2026, Table 28

Rapid transit

BenchmarkUnitLowMedianHighBase yearSource
Busway, NZ completed projectsNZ$m per km$68.0m$68.0m$131m2025Te Waihanga 2026, Table 40 (see busway band check)
Light rail, at-grade (75%+ at grade), OECDNZ$m per km$64.0m$82.0m$102m2025Te Waihanga 2026, Table 39
Light rail, partly tunnelled or elevated, OECDNZ$m per km$123m$175m$251m2025Te Waihanga 2026, Table 39
Light rail, tunnelled or elevated, OECDNZ$m per km$221m$274m$506m2025Te Waihanga 2026, Table 39
Heavy rail, tunnelled or elevated, OECDNZ$m per km$230m$308m$493m2025Te Waihanga 2026, Table 39

Busway band check

Test on Te Waihanga Table 40Result (2025 NZ$m per km)
Completed busways listed$68m, $68m, $131m (three projects)
Median of the three$68m
75th percentile of the three (linear interpolation)$99.5m
Highest completed$131m
Te Waihanga stated figure (comparison only): 'P75 of completed busways' (p.47)$140m: not reproducible from Table 40
75th percentile if the $171m Pakūranga to Botany estimate is added$141m

The $140m figure does not stand as a percentile of completed busways. It lines up with a set that includes the Pakūranga to Botany estimate, which is not a completed cost; that is an inference, and Te Waihanga does not say so. This page now uses $68m to $131m, the full range of completed projects, as the busway band, and shows $140m only as a Te Waihanga stated figure, for comparison. The highest completed cost is used rather than $99.5m because a percentile of three projects is not meaningful. With only three projects, treat any busway rating as indicative.

Buildings (Auckland unless stated)

BenchmarkUnitLowMedianHighBase yearSource
Hospital, new build (NAMP unit costs)NZ$ per m2 GFA$12,107$16,0422023Te Waihanga 2026 (citing NZIER 2023)
Office, investment grade, outside CBD, up to 10 storeysNZ$ per m2 GFA$4,500$5,0002024RLB Riders Digest NZ 2025
Office, walk-up, outside CBDNZ$ per m2 GFA$4,250$4,7502024RLB Riders Digest NZ 2025
Office, investment grade, CBD, up to 10 storeysNZ$ per m2 GFA$5,000$5,5002024RLB Riders Digest NZ 2025
Office, prestige, CBD, 10 to 25 storeysNZ$ per m2 GFA$5,500$6,5002024RLB Riders Digest NZ 2025
Car park, open-deck multi-storeyNZ$ per m2 GFA$1,700$2,3002024RLB Riders Digest NZ 2025
Car park, basement, outside CBDNZ$ per m2 GFA$3,500$4,5002024RLB Riders Digest NZ 2025
Industrial / depot shed, metal clad, 6 m, 4,500 m2NZ$ per m2 GFA$1,200$1,4002024RLB Riders Digest NZ 2025
Aged care, single-storey facilityNZ$ per m2 GFA$4,500$5,5002024RLB Riders Digest NZ 2025
Apartments, up to 10 storeys with liftNZ$ per m2 GFA$5,500$6,0002024RLB Riders Digest NZ 2025
Townhouses, 90 to 120 m2 per unitNZ$ per m2 GFA$2,950$3,4502024RLB Riders Digest NZ 2025
Supermarket / variety storeNZ$ per m2 GFA$3,000$3,6002024RLB Riders Digest NZ 2025

RLB rates are tender-level building costs as at Q4 2024 and exclude GST, land, legal and professional fees, loose furniture and fittings, and site works and drainage. RLB publishes no rate for libraries, pools or community centres. Te Waihanga reports NZ hospital upgrade costs at around 20% above international benchmarks per m2.

Contingency and escalation

Reference-class risk uplift (international)

Project typeMean overrunP50 upliftP80 uplift
Roads22%16%47%
Tunnels36%24%68%
Rail stations43%18%60%
Transmission lines8%0%15%
Wind power12%1%22%
Hospitals23%0%23%

Source: Oxford Global Projects, reference class forecasting.

Escalation signals, 2026

MeasureFigureSource
CGPI civil construction, year to June 20265.2%Stats NZ via NZIER/RLB
CGPI civil construction, June 2026 quarter2.7%Stats NZ via NZIER/RLB
CGPI non-residential, year to June 20262.2%Stats NZ via NBR
CGPI residential, year to June 20262.8%Stats NZ via NBR
NZIER forecast civil, Dec 2026 quarter6.0%NZIER/RLB Aug 2026
NZIER forecast civil, low point H2 20271.8%NZIER/RLB Aug 2026
QV non-residential excl. education, annual2.0%QV, Sept 2026
JLL Asia Pacific tender prices, 20273.8% to 4.7%JLL, Oct 2026

Use the uplift table to judge whether a project's contingency is in a normal range, not as a target. NZIER warns that CGPI civil is a national average across all types of work, so treat it with care for any single project.

What JLL's index covers

3.5% to 4.7%
Global cost growth forecast, 2026
3.1% to 4.2%
Global forecast, 2027
3.8% to 4.7%
Asia Pacific forecast, 2027
8% to 35%
Construction wage rises, 2020 to 2026
Building type (global average)US$ per m2
Office, shell and core2,600 to 3,410
High-rise residential2,280 to 3,710
Industrial and logistics980 to 1,520
  • Based on JLL's Construction Costs Index, Cost Monitor and Projects database: 1,000+ projects, six building types, 14 markets.
  • Annual escalation of 3% to 6% is the new planning baseline, against 2% to 3% before 2020; costs rose 25% to 30% on average over five years, and up to 40% in some markets.
  • Tender prices outran consumer prices most in Germany, Australia and Singapore; they were broadly in line in the UK, Spain, Canada, France and China.
  • Skilled labour shortages are reported by 64% of JLL's markets; electricians and carpenters (64%) and plumbers and HVAC technicians (58%) are named as cost drivers.
  • New Zealand and Auckland are not named in the public summary. The full report, including the list of 14 markets, sits behind a download form.

Use JLL for direction, meaning escalation and labour pressure, not as a local yardstick. Its building rates are global US dollar averages for commercial property, not council infrastructure.

Australian proxies

City (RLB, Q4 2024)CurrencyOffice, Grade A, per m2Warehouse, per m2
AucklandNZD5,000 to 6,6001,200 to 1,500
SydneyAUD3,950 to 5,9001,060 to 1,760
MelbourneAUD3,700 to 5,2001,100 to 1,660
BrisbaneAUD3,900 to 5,4001,260 to 1,860

These figures come from RLB's international table, in local currency and not exchange-rate adjusted, so they are proxies only. On roads, Te Waihanga found NZ urban motorway unit costs similar to Australia's on median and middle-50% range, and NZ construction wages around 35% below Australia's.

If a project is out of band

Documents to request

  • The cost estimate behind the published figure, with its date, price basis and confidence level (P50, P90 or P95).
  • The elemental or trade cost plan from the quantity surveyor, including base cost, contingency and escalation shown separately.
  • Scope quantities: GFA, lane-km or route-km, number of stations or structures, and share of length on bridges or in tunnels.
  • Land and property, consenting, professional fees, client-side management and financing costs, each shown separately.
  • Any independent cost review, peer review or Te Waihanga / Treasury gateway assessment.
  • Comparable projects or benchmarks the organisation used to test the estimate.
  • Procurement approach, number of tenderers, and tender results against the pre-tender estimate.
  • The latest business case with its benefit-cost ratio and the cost figure used in it.

LGOIMA request wording

Request wording
Subject: LGOIMA request: cost basis for {project name}
Under the Local Government Official Information and Meetings Act 1987, please provide the following for {project name}:
1. The current total cost estimate, the date it was prepared, the price base year, and whether it is a P50, P90, P95 or other confidence-level estimate.
2. A breakdown of that estimate into base construction cost, contingency, escalation, land and property, consenting, professional and design fees, client-side management, and financing.
3. The scope quantities the estimate is based on (for example gross floor area in m2, lane-kilometres, route-kilometres, number of stations or structures).
4. Any cost plan or estimate prepared by a quantity surveyor or cost consultant, and any independent cost review or peer review.
5. Any benchmarking of the project's unit cost against other New Zealand or international projects carried out by or for the organisation.
6. For any part of the project already tendered, the pre-tender estimate and the accepted tender price.
If any part of this request is refused or would take substantial collation, please release the remaining parts and tell us which parts are affected. We are happy to receive documents electronically.
City Builders Association

Auckland Council requests go to officialinformation@aucklandcouncil.govt.nz. Send requests about Auckland Transport, Eke Panuku or Watercare projects to that organisation's own official information contact. You can follow CBA's own requests on the LGOIMA tracker.

Sources and checks

Te Waihanga 2025-dollar unit costs unless stated. No rating changes when the busway band top is $131m rather than the Te Waihanga stated figure of $140m. East West Link was excluded: Te Waihanga left it out of its own motorway distribution because of unusual scope, and its lane-km figure comes from diagrams, so the arithmetic multiple is not a reliable finding. We also reviewed the Central Interceptor and the Northcote Community Hub, which are left unrated because no sourced public band exists for wastewater tunnels or community centres. These ratings are a snapshot as at 17 November 2026; several inputs are estimates or envelopes, not outturn costs.

Eastern Busway check

Official figureWhat it coversDateSource
$867mConfirmed budget for the Pakūranga to Botany section. Includes cycling and walking paths, roading improvements and the Reeves Road flyover.October 2021https://ourauckland.aucklandcouncil.govt.nz/news/2021/10/eastern-busway-gets-green-light/
$804mAT's 'current project total' after approving Stages 3c and 4i, which added $198m (Burswood busway, 107 m bridge, Burswood stop, Botany station upgrade). AT does not say whether it covers the whole section; the Botany link through Guys Reserve was unfunded at the time.28 September 2023https://at.govt.nz/about-us/news-events/media-centre/2023-media-releases/approval-of-next-phase-of-eastern-busway-project
$101mNZTA and Auckland Council funding for the Botany link through Guys Reserve. This is an addition, not a project total.February 2026https://at.govt.nz/projects-and-initiatives/eastern-busway
Comparable figure
$867m. It is the only official figure published as the cost of the Pakūranga to Botany section. It is a 2021 budget in 2021 dollars and predates later scope changes.
Length
5 km of busway for Pakūranga to Botany, with 5 stations and 12 km of walking and cycleways (AT project page, updated 26 October 2026). The whole Panmure to Botany busway is 7 km (OurAuckland, October 2021).
Unit cost
$867m ÷ 5 km = $173.4m per km in 2021 dollars, before escalation: 1.32× the $131m band top (1.24× the Te Waihanga stated figure of $140m, comparison only). Above benchmark; escalating to 2025 dollars would raise it. Te Waihanga's own $171m per km gives 1.31×.
Current official total
Not found. $804m plus $101m is $905m, but that is a sum of two figures, not a published total, so it is not used.
Te Waihanga's $856m
A figure used by Te Waihanga that we could not find in any AT or council document. It is lower than the 2021 budget of $867m even though it is stated in 2025 dollars, and Te Waihanga does not explain the gap.

Gaps and limits

  • JLL's 14-market list and city rates are in the gated full report; NZ coverage could not be confirmed.
  • No public 2026 NZ Riders Digest was found; building rates are Q4 2024 and need escalating.
  • QV CostBuilder and Rawlinsons $/m2 rates are subscription-only and not used here.
  • No sourced public benchmark was found for libraries, pools, community centres, or water and wastewater pipes and plants; Watercare projects need a separate source.
  • No published Auckland Council or AT standard unit-cost schedule was found.
  • Bands rest on small samples (for example 25 NZ motorways, 4 NZ hospitals, 3 completed NZ busways) and do not adjust for ground conditions, structures or urban constraints.
  • Proposed roads are rated against the completed-motorway band; the NZTA $17m target is shown as a sensitivity. Te Waihanga's distribution for proposed RoNS (P75 $98.9m per lane-km) is not used as a benchmark because it describes estimates, not delivered costs.
  • Escalation from CGPI is a national average; NZIER cautions against applying it to a single project without care.

Sources

  1. Global Construction Costs Index 2026. JLL, 15 Oct 2026.
  2. Higher construction costs reshape real estate viability, JLL reports. JLL newsroom, 15 Oct 2026.
  3. Understanding capacity upgrade pressures across infrastructure networks. Te Waihanga, 2026.
  4. Making every dollar count. Te Waihanga, Sept 2026.
  5. The lay of the land: Benchmarking NZ's infrastructure delivery costs. Te Waihanga, Dec 2022.
  6. NZIC benchmark report (cost, schedule and overrun reference classes). Oxford Global Projects for Te Waihanga, 2022.
  7. Riders Digest 2025, New Zealand. Rider Levett Bucknall, Feb 2025.
  8. NZIER Forecast Infrastructure Report, construction costs. RLB / NZIER, Aug 2026.
  9. Civil construction inflation to hit 6%, on oil price shocks. NBR, 4 Sept 2026.
  10. Price indexes for the construction industry. Stats NZ.
  11. Diesel rebound drives construction costs upward. QV, 1 Sept 2026.
  12. Eastern Busway gets green light ($867m budget). OurAuckland, Oct 2021.
  13. Approval of next phase of Eastern Busway project ($804m). Auckland Transport, 28 Sept 2023.
  14. Eastern Busway project page ($101m, 5 km). Auckland Transport, Updated 26 Oct 2026.
  15. Te Ara Hauāuru, Northwest Busway Investment Case Summary. NZTA via beehive.govt.nz, April 2025.
  16. Mill Road Stage 1 Investment Case Summary. NZTA via beehive.govt.nz, April 2025.
  17. Regulatory Impact Statement: Tolling Penlink ($830m as at June 2022). Ministry of Transport, 14 Oct 2022.
  18. Delayed again: Penlink opening set for late 2029. Local Matters, 26 Mar 2026.
  19. Financial update: City Rail Link ($5.493bn). OurAuckland, 15 Mar 2023.
  20. City Rail Link project overview (3.45 km tunnels). City Rail Link Ltd.
  21. Warkworth to Te Hana. NZ Infrastructure Pipeline.