Green Lane West: note to the TIDC before item 8.3 (23 November 2026)
On 23 November 2026, Mark Pervan asked that a note be circulated to the Transport and Infrastructure Delivery Committee before item 8.3 on 24 November. The note says the Green Lane West paper does not meet Local Government Act ss77 and 78, and asks the Committee to defer. On 24 November 2026 the Committee deferred its decision to May 2027.

On 23 November 2026, Mark Pervan asked that a note be circulated to the Chair (Cr Andy Baker) and all members of the Transport and Infrastructure Delivery Committee before item 8.3 on 24 November. The note says the Green Lane West paper does not meet Local Government Act ss77 and 78, and asks the Committee to defer.
The note
Mark Pervan (Founder and Director, City Builders Association Limited) wrote to the Senior Governance Advisor for the Transport and Infrastructure Delivery Committee, asking for a note to be circulated to the Chair (Cr Andy Baker) and all members before item 8.3 on 24 November 2026. The note says item 8.3 "does not meet the standard that ss77 and 78 of the Local Government Act 2002 require" and asks the Committee to defer the decision until these gaps are fixed.
The six points
-
Scheme C has no benefit-cost ratio (paras 7, 43). Its bus and productivity benefits are "not quantified in the draft assessment". The options were not assessed on equal terms (s77(1)(b)).
-
About $13.4 million of the up to $16.9 million is unfunded, and the estimates rest on "an early stage of design" (paras 34, 46). Approving "delivery" on that basis is not prudent financial management (ss14(1)(g), 101(1)).
-
Scheme B takes about 116 kerbside spaces west of Manukau Road from 7 to 10am and 3 to 6pm on weekdays, the figure Auckland Transport gave in its November 2025 consultation. The paper does not say so. On 29 October Auckland Transport said it has "not undertaken a parking displacement analysis" (CAS-1414798).
-
Scheme B was never consulted on, which para 27 concedes (s78). Health NZ's requested traffic assessment and lane-hours review are unanswered.
-
The paper says the layout "has been tested through traffic modelling" but provides no modelling outputs. Auckland Transport released a modelling pack on 16 September 2026 (CAS-1395336), yet none of it is in the paper. No crash data is provided.
-
The parking information sought under CAS-1411140 remains unreleased, and Ombudsman case 049295 is open.
Status
Status: sent. Outcome (updated 27 November 2026): on 24 November 2026 the Committee did not choose a scheme. It deferred the decision, asked for detailed design work on both Green Lane West options, and said a final decision will be made in May 2027 (Newsroom, 25 November 2026). The official minutes had not been published when this was checked on 27 November 2026.
Related correspondence
The full Green Lane West correspondence chain is on the earlier objection page. Related official information requests are recorded on the LGOIMA tracker.
PDF edition
Frequently asked questions
What did CBA ask the Transport and Infrastructure Delivery Committee to do about Green Lane West item 8.3?
On 23 November 2026, Mark Pervan asked for a note to be circulated to the Chair (Cr Andy Baker) and all members before item 8.3 on 24 November 2026. The note says the paper does not meet the standard that ss77 and 78 of the Local Government Act 2002 require, and asks the Committee to defer the decision until the gaps are fixed. On 24 November 2026 the Committee did not choose a scheme. It deferred the decision, asked for detailed design work on both options, and said a final decision will be made in May 2027.
Why does CBA say the Green Lane West paper is not at the decision-making standard?
The note sets out six points: Scheme C has no benefit-cost ratio (paras 7, 43) and the options were not assessed on equal terms (s77(1)(b)); about $13.4 million of the up to $16.9 million is unfunded and the estimates rest on "an early stage of design" (paras 34, 46); the paper does not state that Scheme B takes about 116 kerbside spaces west of Manukau Road from 7 to 10am and 3 to 6pm on weekdays, and on 29 October Auckland Transport said it has "not undertaken a parking displacement analysis" (CAS-1414798); Scheme B was never consulted on, which para 27 concedes (s78), and Health NZ's requested traffic assessment and lane-hours review are unanswered; the paper says the layout "has been tested through traffic modelling" but provides no modelling outputs or crash data, even though Auckland Transport released a modelling pack on 16 September 2026 (CAS-1395336); and the parking information sought under CAS-1411140 remains unreleased, with Ombudsman case 049295 open.
Where is the earlier Green Lane West correspondence?
The full correspondence chain is on the earlier Green Lane West objection page (https://thecitybuilder.com/article/objection-better-journeys-on-green-lane-west-pending). Related official information requests are recorded on the LGOIMA tracker (https://thecitybuilder.com/lgoima).
Join the discussion
Community members are invited to add perspective, evidence, or a sharp question. Be specific and keep it civil.
No comments yet. Be the first to weigh in.
Written by Mark Pervan, Director, City Builders Association Limited
Mark Pervan is the founder and director of City Builders Association Limited, an Auckland civic think tank funded by membership and voluntary contributions. He has run manufacturing plants, with global sourcing and supply chain management in the same role, and has been project manager on multiple commercial and residential building projects. He was also responsible for product design and development across multiple mediums, and served as sales and marketing manager. He is a company director and business owner, including as a director of Idea Foundry. Since 18 November 2026 he has been Chair of the Dominion Road Business Association (DRBA). He served three years as an elected member of the Puketāpapa Local Board (2022–2025) and was a council candidate for the Albert-Eden-Puketāpapa ward of Auckland Council.