New North Road parking-bay removal: AT decision released; questions remain
Auckland Transport issued its LGOIMA decision on New North Road parking-bay removal on 6 November 2026. CBA has sent a further-information request. Questions remain over evidence, transparency and photo-op staging of the works.

New North Road parking-bay removal: AT decision released; questions remain
City Builders Association (CBA) Correspondence · 6 November 2026
Auckland Transport (AT) issued its decision on LGOIMA file CAS-1418501-T6D5Y4 on 6 November 2026, about 11:35am NZDT, on the due date. CBA's framing of this update is: AT decision released; questions remain over evidence, transparency and photo-op staging. A further-information request has been sent. As at 12:07pm NZDT on 6 November 2026, there was no acknowledgement, new case number, new due date or substantive reply.
This page is the public record of that correspondence. It does not republish AT-released files.
Status
- 6 November 2026, ~11:35am NZDT: AT decision issued on CAS-1418501-T6D5Y4 (due date).
- 6 November 2026, ~12:05pm NZDT: CBA further-information request sent from
founder@to AT Official Information (threaded), asking AT to keep the matter under CAS-1418501-T6D5Y4 or to acknowledge any new LGOIMA request with a case number and due date. - As at 12:07pm NZDT, 6 November 2026: no acknowledgement, no new case number, no new due date, and no substantive reply recorded.
- Albert-Eden Local Board / TCC: on 18 September 2026, under Report ID 19513, approved NSAAT replacing P30 and the 4-6pm clearway, drawing AT/AELB/19513/LZ/632 Rev A dated 12 February 2026.
What the TCC report records
The TCC report says investigation confirmed parked vehicles obstructed two northbound lanes and records an ANOP Fit Assessment.
AT refused the requested safety, traffic and bus-lane assessment information under LGOIMA s17(e), saying it does not exist. No investigation record, traffic counts, crash or near-miss evidence, or ANOP output was released.
CBA concern: a report that cites investigation findings and an ANOP Fit Assessment sits uneasily alongside a s17(e) "does not exist" refusal for the underlying assessment material. That tension is why CBA has asked AT to reconcile the refusal with the report and to release supporting evidence.
Option wording and what triggered the proposal
The report identifies northbound lanes, but Option 2 concerns reducing southbound traffic to one lane.
The report attributes the proposal to an internal Road Network Optimisation request. AT's letter adds four Quick Fix requests, six resident cases and an MP request. None of those source requests were released.
CBA concern: the public record should show what was asked for, what options were assessed, and which direction of travel the approved controls address. The option discrepancy and the unreleased source requests are part of the further-information ask.
Consultation
- 121-property letter drop.
- Three responses, all supportive.
- MABA supported the change and requested parking elsewhere; that request was treated as out of scope.
- No public meeting and no consultation close-out are recorded in the material summarised here.
Works staging and the Mayor (timing only)
Released emails show works on 30 September were deliberately staged so the Mayor could get "action shots", with contractor stand-down costs to be agreed.
Important limit on what that shows: establish influence over timing and staging only, not over the decision itself. All released messages postdate the 18 September 2026 approval. This update does not claim the emails prove Mayor involvement in the approval decision.
AT has not said whether it searched the Mayor's office records from 1 August to 18 September. A media runsheet and other attachments were not released, and were not individually listed with withholding grounds. The actual delegation instrument was not supplied.
CBA concern: decisions about public road space must rest on evidence, lawful delegation and transparent records. They must not become a mechanism to justify a chosen outcome. Photo-op staging and stand-down costs are relevant to how works were delivered and what they cost the public, not a substitute for the decision record.
Further-information request (6 November 2026)
Mark sent a threaded further-information request from founder@ to AT Official Information at about 12:05pm NZDT on 6 November 2026. It asks AT to:
- Reconcile the s17(e) refusal with the TCC report's investigation and ANOP Fit Assessment references.
- Release supporting evidence and the source requests (Road Network Optimisation, Quick Fix, resident cases, MP request), or explain withholding with grounds.
- Clarify the northbound / southbound Option 2 discrepancy.
- Confirm the scope of any pre-decision search of Mayor's office records (1 August to 18 September).
- Disclose photo-op stand-down costs and the works / sign chronology.
- Release or individually list withheld attachments with withholding grounds.
- Provide the actual delegation instrument.
CBA asked AT to keep the matter under CAS-1418501-T6D5Y4, or to acknowledge any new LGOIMA request with a case number and due date.
What this page does not claim
- It does not name AT or council staff.
- It does not republish or upload AT-released files.
- It does not assert established misconduct.
- It does not treat photo-op staging emails as proof that the Mayor decided the 18 September approval.
Next step
Awaiting AT acknowledgement or substantive reply. This page will be updated when a case number, due date or decision is received.
Join the discussion
Community members are invited to add perspective, evidence, or a sharp question. Be specific and keep it civil.
No comments yet. Be the first to weigh in.
Written by Mark Pervan, Director, City Builders Association Limited
Mark Pervan is the founder and director of City Builders Association Limited, an Auckland civic think tank funded by membership and voluntary contributions. He has run manufacturing plants, with global sourcing and supply chain management in the same role, and has been project manager on multiple commercial and residential building projects. He was also responsible for product design and development across multiple mediums, and served as sales and marketing manager. He is a company director and business owner, including as a director of Idea Foundry. He served three years as an elected member of the Puketāpapa Local Board (2022–2025) and was a council candidate for the Albert-Eden-Puketāpapa ward of Auckland Council.
Mark on LinkedIn